G
Gil
Hi everyone,
I (think I) understand the logic behind actual work values replace
work values, and I understand that in order to compare between
original plan and reality, I need to compare the baseline values with
actuals.
That said, What is the effective meaning of "planned" line in a
timesheet? The resource manager see two identical lines, and cannot
tell what was suppose to happen, e.g. how many hours the resource was
scheduled to work, since now "planned" line contains same values as
"actual" line. Should the resource manager look for this information
in another view instead?
Also, when the project manager check the task updates that were
submitted to him by team members, he see the same values on "Work" and
"Actual Work". Again, what is the point of this fields in the process
of accepting task updates? What information can be obtained? Is there
anyway to add "Baseline Work" for the "task updates" view?
Thanks for any help and thoughts
Gil
I (think I) understand the logic behind actual work values replace
work values, and I understand that in order to compare between
original plan and reality, I need to compare the baseline values with
actuals.
That said, What is the effective meaning of "planned" line in a
timesheet? The resource manager see two identical lines, and cannot
tell what was suppose to happen, e.g. how many hours the resource was
scheduled to work, since now "planned" line contains same values as
"actual" line. Should the resource manager look for this information
in another view instead?
Also, when the project manager check the task updates that were
submitted to him by team members, he see the same values on "Work" and
"Actual Work". Again, what is the point of this fields in the process
of accepting task updates? What information can be obtained? Is there
anyway to add "Baseline Work" for the "task updates" view?
Thanks for any help and thoughts
Gil