reza
Hi All,
1. in my task i am using Timephased View, then one of resource fill that
column with 10h. Then, that resoruce create timesheet, after he click Import
Task Progress... planned row change from 8h to 10h....is it like that? can
planned work stay at 8h???
2. standard for work hours is 8h, if in my timesheet or my task (timephased
view) we fill with 10h, can that 10h divide it to 8h and 2h...so 8h will set
to row actual work and 2h will fill into overtime row? can PS 2007 do that?
thanks for your help
reza
1. in my task i am using Timephased View, then one of resource fill that
column with 10h. Then, that resoruce create timesheet, after he click Import
Task Progress... planned row change from 8h to 10h....is it like that? can
planned work stay at 8h???
2. standard for work hours is 8h, if in my timesheet or my task (timephased
view) we fill with 10h, can that 10h divide it to 8h and 2h...so 8h will set
to row actual work and 2h will fill into overtime row? can PS 2007 do that?
thanks for your help
reza