Planning Projects and using Outlook Calendar

J

J. Kümpel

H

I'm trying to set up Project Pro 2003, Project Server 2003 and Outlook 2003
The integration from Project to Outlook is working fine, but when i plan my projects it dosn't handel if a resource i booked in the outlook calendar for another non-project related task
This is not vacation, other tasks like a sales or customer meeting e.g

Is there any posibillty that project can handle this ??

Thanks
Jesper
 
G

Gary L. Chefetz

Jesper:

The only way the system can manage tasks is if they're created in project
plans. There's no mechanism available for examining Outllook-spawned tasks
and appointments. If you wrote one, you'd likley have a marketable addin!




J. Kümpel said:
Hi

I'm trying to set up Project Pro 2003, Project Server 2003 and Outlook 2003.
The integration from Project to Outlook is working fine, but when i plan
my projects it dosn't handel if a resource i booked in the outlook calendar
for another non-project related task.
 
J

J. Kümpel

Thanks Gar

But in the Project 2002 Server there was a feature to import outlook calendar entries !
Isn't this avalible any more?

Regards Jespe

----- Gary L. Chefetz chefetz org> wrote: ----

Jesper

The only way the system can manage tasks is if they're created in projec
plans. There's no mechanism available for examining Outllook-spawned task
and appointments. If you wrote one, you'd likley have a marketable addin

--

Gary Chefetz [MVP
http://www.msprojectexperts.co
We wrote the book on Project Serve


J. Kümpel said:
H 2003
The integration from Project to Outlook is working fine, but when i pla
my projects it dosn't handel if a resource i booked in the outlook calenda
for another non-project related task
 
G

Gary L. Chefetz [MVP]

Jesper:

They didn't import as tasks.




J. Kümpel said:
Thanks Gary

But in the Project 2002 Server there was a feature to import outlook calendar entries !!
Isn't this avalible any more??

Regards Jesper

----- Gary L. Chefetz chefetz org> wrote: -----

Jesper:

The only way the system can manage tasks is if they're created in project
plans. There's no mechanism available for examining Outllook-spawned tasks
and appointments. If you wrote one, you'd likley have a marketable addin!




Outlook plan
my projects it dosn't handel if a resource i booked in the outlook calendar
for another non-project related task.
 
J

J.Kümpel

Gary,
I don't want them as tasks. I just want the time booked i my Project caledar for the resource !

Regards Jesper
 
G

Gary L. Chefetz [MVP]

Jesper:

You're mistaken if you think that it worked that way in 2002. It simply
didn't and doesn't in the new version. When Outlook tasks are shown in the
timesheet, they have absolutely no effect on the system other than providing
a convenience for the resource.
 