I want to change an existing project from the standard calendar from the standard calendar to the 24 hrs calendar.
Used 'Project', "Change working time" and selected calendar '24 hrs'. I see the hours in that dialog box change.
But then when I click OK, my project is still on the Std calendar, and if I click on 'Change work time' again, I see the calendar has always been 'Standard'.
Any idea why it won't change?
Thanks a lot,