H
HookEm
Is there a way to set up the enterprise resource pool or configure individual
project settings to support the scenario described below?
Scenario:
I have a team of about 30 or so developers in my enterprise resource pool.
Some resources are dedicated to particular projects but others (such as doc
writers, QA personnel, etc.) will be assigned to tasks across multiple
projects. Some of the projects are "lower priority" than the other projects
(IOW, it doesn't matter if the duration of a task on a low priority project
increases because the resource is needed on a higher priority project).
Re-task Example:
Two projects: projA (high priority) and projB (lower priority).
Doc resource: res1
Res1 is assigned several known duration tasks on low priority projB: TaskB1,
TaskB2, TaskB3, etc.
The project owner for projA decides that they need Res1 for a known duration
task to be added to projA schedule (to be added TaskA1).
Current Behavior:
If the projA owner adds Task1A and assigns it to Res1 then the duration gets
automatically sized based on the tasks assigned to Res1 on projB. IOW, Res1
is "locked" for the time periods identified by TaskB1, TaskB2, TaskB3.
Is there a way to set this up so that projA owner can add Task1A and set the
duration to what the projA schedule needs and the projB task durations are
automatically resized accordingly? IOW, the duration for new Task1A should
"trump" the durations for existing tasks TaskB1, TaskB2, TaskB3.
project settings to support the scenario described below?
Scenario:
I have a team of about 30 or so developers in my enterprise resource pool.
Some resources are dedicated to particular projects but others (such as doc
writers, QA personnel, etc.) will be assigned to tasks across multiple
projects. Some of the projects are "lower priority" than the other projects
(IOW, it doesn't matter if the duration of a task on a low priority project
increases because the resource is needed on a higher priority project).
Re-task Example:
Two projects: projA (high priority) and projB (lower priority).
Doc resource: res1
Res1 is assigned several known duration tasks on low priority projB: TaskB1,
TaskB2, TaskB3, etc.
The project owner for projA decides that they need Res1 for a known duration
task to be added to projA schedule (to be added TaskA1).
Current Behavior:
If the projA owner adds Task1A and assigns it to Res1 then the duration gets
automatically sized based on the tasks assigned to Res1 on projB. IOW, Res1
is "locked" for the time periods identified by TaskB1, TaskB2, TaskB3.
Is there a way to set this up so that projA owner can add Task1A and set the
duration to what the projA schedule needs and the projB task durations are
automatically resized accordingly? IOW, the duration for new Task1A should
"trump" the durations for existing tasks TaskB1, TaskB2, TaskB3.