Please Help ! Rolling Up % Complete in Groupings

K

Kamal Carlos Saade

In the Project Center of Project Server I am attempting to roll up the %
Complete column in the grouping. Since it is a text field it is not rolling
up. Is there a way to roll up this field or custimize a calculated field to
roll up? and provide me with the data required?

Thx.
 
J

JosieMarley

I don't think the Project Centre works that way, but maybe someone else can
say for certain.

Perhaps you could create a new schedule with the projects you are interested
in inserted into it (Insert, Project...) - then I think the % Complete of
that schedule will be calculated based on the % complete of the inserted
schedules.
 