Z
Zcema06
Hi
I am using project 2003.
As you know the "duration" field is calculated from the end and start dates
entered, a gantt chart of the "duration" is then plotted.
I have created a new column (field) called Actual Duration (in hours) and I
would like project to plot the gantt chart of the Actual Duration column and,
update the start and end dates from the Actual duration column instead of
doing so from the default "duration" field.
Any help will be appreciated.
Thanks.
I am using project 2003.
As you know the "duration" field is calculated from the end and start dates
entered, a gantt chart of the "duration" is then plotted.
I have created a new column (field) called Actual Duration (in hours) and I
would like project to plot the gantt chart of the Actual Duration column and,
update the start and end dates from the Actual duration column instead of
doing so from the default "duration" field.
Any help will be appreciated.
Thanks.