D
Deva
I want our PM's to view only generic resources from enterprise pool. They
request resources through generic resources to resource manager, when the
resources manager assigns and commits the actual resources to the plan. The
PM should see only committed resources along with enterprise generic
resources. Can we achieve this by modifying the security categories? If yes
could you please tell me the exact steps?
request resources through generic resources to resource manager, when the
resources manager assigns and commits the actual resources to the plan. The
PM should see only committed resources along with enterprise generic
resources. Can we achieve this by modifying the security categories? If yes
could you please tell me the exact steps?