Leonid --
I'm not sure I understand your question. When the PM assigns a task to a
resource and publishes the project, the resource can see the task on his/her
My Tasks page in PWA, can enter progress against the task, and then submit a
task update to the PM. The PM can see and approve the task update on the
Task Updates page in PWA. To see the tasks assigned to any resource in a
project, the PM can always open the project in Project Professional 2007 and
apply the Resource Usage view. To see what tasks are assigned to a resource
in all projects, the PM can go to the Resource Center page in PWA, select
the name of the resource, and then click the View Assignments button. Hope
this helps.