PMs want to see assigned task

L

Leonid

When PM assign a task to team member, team members could see and execute
these task at their My task page.

How PM can see task he assigned and which should be completed?
 
D

Dale Howard [MVP]

Leonid --

I'm not sure I understand your question. When the PM assigns a task to a
resource and publishes the project, the resource can see the task on his/her
My Tasks page in PWA, can enter progress against the task, and then submit a
task update to the PM. The PM can see and approve the task update on the
Task Updates page in PWA. To see the tasks assigned to any resource in a
project, the PM can always open the project in Project Professional 2007 and
apply the Resource Usage view. To see what tasks are assigned to a resource
in all projects, the PM can go to the Resource Center page in PWA, select
the name of the resource, and then click the View Assignments button. Hope
this helps.
 
L

Leonid

yes, it's right. I knew this way, but hoped there is way to see assigned
tasks in My Tasks for PM.
 
D

Dale Howard [MVP]

Leonid --

The only way for the PM to see the tasks on his/her own My Tasks page is to
change the Assignment Owner value for each task and to choose him/herself as
the Assignment Owner. After publishing the project, the system will remove
the tasks from the My Tasks page for each resource and place the tasks on
the My Tasks page for the PM. This means that the PM must status each task.
Are you sure that it what you want to do? If so, go for it. If not, then
the PM cannot see the tasks of his/her resources on his/her own My Tasks
page. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top