N
NSHAH
BACKGROUND
We have been using MS ProjServer 2003 for little over a month. We currently
have 30 plans and about 250 resources (Enterprise Rsrc Pool) in our
Production environment. On an avg. we have 5 to 7 PMs accessing the Project
Pro at any given time.
We have one Master Plan that consists of 17 sub-projects. The total number
of tasks - 6300. 3650 of the tasks have some sort of depdencies. About 250 of
those dependencies are "inter-project" in nature - depedency between two
project tasks.
PROBLEM
Poor performance when working in the Master Plan. It takes 5 to 10min. to
open the plan. 30min. to save the plan. Anytime we add a new task or delete
an existing task the response time is 5 to 8 seconds. Same when changing or
adding dependencies.
We tried puting the same environment in a more beefed up hardware
architecture and stil the same issue.
ANY SUGGESTIONS? IS OUR APPROACH TO THE MASTER PROJECT IS WRONG? OR IS IT MS
PROJ SERVER PERFORMANCE CONSTRAINT? RESPONSE TIME IS REALLY KILLING US.
NSHAH
We have been using MS ProjServer 2003 for little over a month. We currently
have 30 plans and about 250 resources (Enterprise Rsrc Pool) in our
Production environment. On an avg. we have 5 to 7 PMs accessing the Project
Pro at any given time.
We have one Master Plan that consists of 17 sub-projects. The total number
of tasks - 6300. 3650 of the tasks have some sort of depdencies. About 250 of
those dependencies are "inter-project" in nature - depedency between two
project tasks.
PROBLEM
Poor performance when working in the Master Plan. It takes 5 to 10min. to
open the plan. 30min. to save the plan. Anytime we add a new task or delete
an existing task the response time is 5 to 8 seconds. Same when changing or
adding dependencies.
We tried puting the same environment in a more beefed up hardware
architecture and stil the same issue.
ANY SUGGESTIONS? IS OUR APPROACH TO THE MASTER PROJECT IS WRONG? OR IS IT MS
PROJ SERVER PERFORMANCE CONSTRAINT? RESPONSE TIME IS REALLY KILLING US.
NSHAH