M
Macrofinder
I currently have many Project Schedules linked to my schedule. When a
Start/Finish field is changed in one schedule, it pushes my Start/Finish
fields and can move my entire network. I have a macro set up to copy
Start/Finish to Date1/Date4, daily.
What I am trying to capture is if my Project Start does not equal Date1,
then put a #1 in Cost2, and if Finish does not equal Date4, put a #2 in
Cost2. I would also like a message box that says, "The Start/Finish fields
have been changed," if in fact the Start/Finish dates are altered by another
schedule. I hope this makes sense.
Start/Finish field is changed in one schedule, it pushes my Start/Finish
fields and can move my entire network. I have a macro set up to copy
Start/Finish to Date1/Date4, daily.
What I am trying to capture is if my Project Start does not equal Date1,
then put a #1 in Cost2, and if Finish does not equal Date4, put a #2 in
Cost2. I would also like a message box that says, "The Start/Finish fields
have been changed," if in fact the Start/Finish dates are altered by another
schedule. I hope this makes sense.