R
RKT
Hello
on my analyzer page i have a cube that goes by week and resource and shows
both Work and Availability. It seems that each employees Avail becomes blank
when I scroll over to the end of their scheduled work. I would assume as I
have the Enterprise Options set out for 12 months and everyone is on the
identical calendar that if there was an issue with either of these the
everyone's Avail would go blank at the same spot. This is not the case. It
goes blank when the end of their scheduled work is reached.
I am running MS Proj Server 2003 with SP1.
Any ideas?
on my analyzer page i have a cube that goes by week and resource and shows
both Work and Availability. It seems that each employees Avail becomes blank
when I scroll over to the end of their scheduled work. I would assume as I
have the Enterprise Options set out for 12 months and everyone is on the
identical calendar that if there was an issue with either of these the
everyone's Avail would go blank at the same spot. This is not the case. It
goes blank when the end of their scheduled work is reached.
I am running MS Proj Server 2003 with SP1.
Any ideas?