Jeff --
To show which resources specifically report to each Resource Manager, there
are at least three things you need to do:
1. In the Enterprise Global, populate the RBS field with the org chart
information for your company
2. In the Enterprise Resource Pool, set each resource (including their
Resource Managers) at the proper place in the RBS field to show who reports
to whom
3. In the Resources section of the My Resources category in PWA, you will
probably want to select the "Only the resources specified below" option,
along with selecting the three check boxes below the list of resources
This is how you show the Project Server database who reports to whom, and
the result will control the names displayed in the Resources page of PWA. I
cannot go into much depth in my answer as a lot depends on how your company
is organized.
To set the timescale to Years Over Months as the level of zoom, do the
following in each project and each enterprise template:
1. Apply the Gantt Chart view, then double-click the Timescale Bar
2. In the Timescale dialog box, click the Middle Tier tab
3. Select "Years" as the Units value, and set the Count value to "1"
4. Click the Bottom Tier tab
5. Select "Months" as the Units value and set the Count value to "1"
6. Click OK
7. Save the project
When you publish your projects, project information is populated
automatically in the OLAP cube the next time the cube is rebuilt. Have you
made certain that your OLAP Cube is being built for you on a regular basis?
Once the information is in the OLAP Cube, you will need to create one or
more Portfolio Analyzer views to show the type of data that your finance
people want to see. Your finance people will also need to have User
accounts created for them in PWA in order for them to see these views. From
there, they can save the Pivot Table information from the Portfolio Analyzer
to Excel. Hope these answers help.