Jax EPM
I have seen other users post regarding this issue but have not seen a
possible resolution through my searches. Basically to quote another
user :
"When I insert the 'Availability' field on portfolio analyzer views
where we
have "Resource" and "Projects" as Row Fields, many projects are
displayed
under a resource's name that they are not assigned to or even on the
project
team. If I remove the Availability field, then only the projects that
resources have assignments in are displayed under their names."
This behavior started after we updated Project Server 2003 with SP2a
and it has degraded the performance of the views to an unacceptable
level due to the sheer number of projects being displayed per
resource.
Does anyone know of a fix for this issue? Any help would be
appreciated.
Thanks much,
A Frustrated PMO
possible resolution through my searches. Basically to quote another
user :
"When I insert the 'Availability' field on portfolio analyzer views
where we
have "Resource" and "Projects" as Row Fields, many projects are
displayed
under a resource's name that they are not assigned to or even on the
project
team. If I remove the Availability field, then only the projects that
resources have assignments in are displayed under their names."
This behavior started after we updated Project Server 2003 with SP2a
and it has degraded the performance of the views to an unacceptable
level due to the sheer number of projects being displayed per
resource.
Does anyone know of a fix for this issue? Any help would be
appreciated.
Thanks much,
A Frustrated PMO