My users are updating their timesheets daily. The project managers are accepting the updates and pushing them into Project Pro correctly. That is, the actual times reported by the resources are correct in the project plan
Enter the problem
I have a Portfolio Analyzer view that displays projects as one axis and and resources as the other axis. The total field is Actual work. In this view a user who has 10 actual hours on the project will show up in the cube as 40 hours
Any ideas why the cube does not display what is in the projects
Thanks
Ryan
Enter the problem
I have a Portfolio Analyzer view that displays projects as one axis and and resources as the other axis. The total field is Actual work. In this view a user who has 10 actual hours on the project will show up in the cube as 40 hours
Any ideas why the cube does not display what is in the projects
Thanks
Ryan