Can someone tell me why some of my projects' 'Actual Cost' do not appear in
the Portfolio Analyzer?
If I view 'Task Actual Cost' instead, in the case were we extended the OLAP
to capture task level data, then the actuals for all the projects in question
are there and contain the correct values.
Note, we enter actuals in the project files manually. Could this have
something to do with it? Yet, all the projects' Actual Cost display
perfectly fine in the Project Center! Why would there a discrepency between
some project files between Project Center and Portfolio Analyzer exist.
Any suggestions?
/Spiro Theopoulos
the Portfolio Analyzer?
If I view 'Task Actual Cost' instead, in the case were we extended the OLAP
to capture task level data, then the actuals for all the projects in question
are there and contain the correct values.
Note, we enter actuals in the project files manually. Could this have
something to do with it? Yet, all the projects' Actual Cost display
perfectly fine in the Project Center! Why would there a discrepency between
some project files between Project Center and Portfolio Analyzer exist.
Any suggestions?
/Spiro Theopoulos