A
Andrea
Hi,
we have problems with our Portfolio Analyzer. I have created a new project
with assignments and I have republished the project. Then, I rebuild the
cube and once it is completly generated I go in Resource Portfolio
Analyzer and then look to a resource assigned to a task in the project I
have just
created. The work hours are blank and in the project plan it is 500 hours of
work.
It appears that there is a problem with the new project I have created
because when I modify projects that already exist, all the changes are
reflected in the portfolio analyzer.
Do you have any idea?
Thanks
Andrea
we have problems with our Portfolio Analyzer. I have created a new project
with assignments and I have republished the project. Then, I rebuild the
cube and once it is completly generated I go in Resource Portfolio
Analyzer and then look to a resource assigned to a task in the project I
have just
created. The work hours are blank and in the project plan it is 500 hours of
work.
It appears that there is a problem with the new project I have created
because when I modify projects that already exist, all the changes are
reflected in the portfolio analyzer.
Do you have any idea?
Thanks
Andrea