H
harvey
Good morning
I have the following view in the Analyzer:
Resource Busines Unit Resource Project Availability Work
Utilization
BU1 RES1 PROJ1 100H 100H
100%
PROJ2 100H
50H 50%
RES2 PROJ1 0H
PROJ2 0H
My questions are:
1. why does the view show projects under resources when the resource is
not attached to the project and has no work?
2. is it possible to restrict the view to those resources where
availability is > zero?
Thank you, Harvey
I have the following view in the Analyzer:
Resource Busines Unit Resource Project Availability Work
Utilization
BU1 RES1 PROJ1 100H 100H
100%
PROJ2 100H
50H 50%
RES2 PROJ1 0H
PROJ2 0H
My questions are:
1. why does the view show projects under resources when the resource is
not attached to the project and has no work?
2. is it possible to restrict the view to those resources where
availability is > zero?
Thank you, Harvey