Portfolio Analyzer view: Local Resources and Tasks only work

A

AI

Hi:

Recently we are seeing that almost all the projects in portfolio analyzer
view for the following report shows "Local Resources" and "Tasks Only Work"
with 0.0h and $0.00 for Actual Work and Actual Cost respectively.

Report Structure (pivot table) is as follows.

Filter area: All Dates
Column area:
Actual Work Actual
Hours

Row area: Project . Resources

Earlier this would happen only on projects on which PMs assigned actual work
on local resources or Tasks Only work accidentally.

Does anybody knows why this is so prevalent on teh OLAP Pivot table and how
can this be curbed.

Please advise.

Thanks,
AI
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top