Portfolio Anaylzer (PA) is not showing correct Resource Timesheet

E

EPM Consultant

Issue:

Portfolio Anaylzer (PA) is not showing correct Resource's correct Actual
Protected hour's value. For e.g. It shows 94 total actual protected hours
against a resource but correct figure is 106 hours

Situation:

In View Resource assignment (with all assignments selected option), it shows
106 hrs work in April month. The system shows matched Actual work/Actual
Protected hours in Project Pro or in PWA so data is consistent and has been
approved by Manager.
I don't know why PA is not showing correct information although Cube builds
every night and I checked and it was successful last night.

Note: I checked another resource data and that was correct. I have this
issue only with one user.

Any suggestion why? and any recommendations to get solve it.

Earliest response would be highly appreciated.