N
Noel
Folks,
We currently use EPM 2007 and will be upgrading to Project Server 2010 soon!
Looking for some guidance in what happens when a "concept" (project) moves
from the Portfolio to the actual Project schedule (EPM) in terms of:-
Our requirements for the portfolio optimisation process requires diverse
selection of fields to be populate, upfront to allow the viewing of data, I’m
assuming that this info will come across as project information data?
Is there a limit on how much / many data fields I can have in the Portfolio
environment?
Can I select a pre determined template for this project to use or will it
just pickup the default Global schedule template?
Answers greatly appreciated
We currently use EPM 2007 and will be upgrading to Project Server 2010 soon!
Looking for some guidance in what happens when a "concept" (project) moves
from the Portfolio to the actual Project schedule (EPM) in terms of:-
Our requirements for the portfolio optimisation process requires diverse
selection of fields to be populate, upfront to allow the viewing of data, I’m
assuming that this info will come across as project information data?
Is there a limit on how much / many data fields I can have in the Portfolio
environment?
Can I select a pre determined template for this project to use or will it
just pickup the default Global schedule template?
Answers greatly appreciated