M
MAS
I am not sure if there is where I should post this. If there is a more
appropriate site, please let me know. I am trying to do some
selection/analysis of projects that I have entered into PPS. The
documentation states that after having established the business driver
priorities and having determined the priorities for projects based on that, a
"Load Constraints from Attributes" dialog should open. I do not get this
dialog so I can not add constraints to the selection process. What am I doing
wrong or what have I not set correctly? Thank you in advance for your help.
appropriate site, please let me know. I am trying to do some
selection/analysis of projects that I have entered into PPS. The
documentation states that after having established the business driver
priorities and having determined the priorities for projects based on that, a
"Load Constraints from Attributes" dialog should open. I do not get this
dialog so I can not add constraints to the selection process. What am I doing
wrong or what have I not set correctly? Thank you in advance for your help.