Portfolio tracking data

A

Alejandro

Hi, i´m using portfolio server to track some projects and i have this problem..

After a project is created and moved forward in workflow to the manage
phase, the baseline data is stored.. that's ok... but i need to reverse the
workflow to modify the budgeted costs and resources.. and then forward
again.. but the baseline is not overwrited, this data is cumulative... so
now.. the project has a correct budget data but the baseline data is
corrupted...

Somebody knows how to delete the baseline and tracking data for a specific
project to avoid this issue..?

tks,
Alejandro
 
D

Dharmesh Patel

Hi there,

for you to be able to do this, i think you will need to go back in the
workflow, and then it will be possible.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top