Hi, i´m using portfolio server to track some projects and i have this problem..
After a project is created and moved forward in workflow to the manage
phase, the baseline data is stored.. that's ok... but i need to reverse the
workflow to modify the budgeted costs and resources.. and then forward
again.. but the baseline is not overwrited, this data is cumulative... so
now.. the project has a correct budget data but the baseline data is
corrupted...
Somebody knows how to delete the baseline and tracking data for a specific
project to avoid this issue..?
tks,
Alejandro
After a project is created and moved forward in workflow to the manage
phase, the baseline data is stored.. that's ok... but i need to reverse the
workflow to modify the budgeted costs and resources.. and then forward
again.. but the baseline is not overwrited, this data is cumulative... so
now.. the project has a correct budget data but the baseline data is
corrupted...
Somebody knows how to delete the baseline and tracking data for a specific
project to avoid this issue..?
tks,
Alejandro