Possible enterprise resource fields for PWA View?

A

Al Himler

In Project Profession, Resource Usage view, you can see a resource and the
number of hours that they are planned for each specific task. I was asked by
my manager if I could present a similar view in PWA.

The idea would be to list each resource saved in Project Server and then to
show their planned utilization over each of the next 4 or 5 weeks. Something
like:

Bob Smith 40h 40h 24h 24h 40h
John Doe 24h 40h 16h 40h 40h

Anybody know if it is possible to set up a formula on a set of 5 fields that
shows each person's utilization like this?

Thanks,

Al
 
D

Dale Howard [MVP]

Al --

Navigate to the Resource Center page in PWA and then click the View Resource
Assignments link in the sidepane on the left. This feature will provide
what you need, I believe. Hope this helps.
 
D

Dale Howard [MVP]

Al --

You're the man! :)





Al Himler said:
Dale, that is seriously a big time savings for me...thanks! I clicked on
the
Timesheet Format and there it was. The only thing missing was being able
to
see multiple weeks at a time. 30 seconds later, using "View Options" I
had
the date range set and the Units set to "weeks"...voila, I've got
it...excellent!! I'll be a hero at the office tomorro ;-)

Thanks!

Al
 