A
Al Himler
In Project Profession, Resource Usage view, you can see a resource and the
number of hours that they are planned for each specific task. I was asked by
my manager if I could present a similar view in PWA.
The idea would be to list each resource saved in Project Server and then to
show their planned utilization over each of the next 4 or 5 weeks. Something
like:
Bob Smith 40h 40h 24h 24h 40h
John Doe 24h 40h 16h 40h 40h
Anybody know if it is possible to set up a formula on a set of 5 fields that
shows each person's utilization like this?
Thanks,
Al
number of hours that they are planned for each specific task. I was asked by
my manager if I could present a similar view in PWA.
The idea would be to list each resource saved in Project Server and then to
show their planned utilization over each of the next 4 or 5 weeks. Something
like:
Bob Smith 40h 40h 24h 24h 40h
John Doe 24h 40h 16h 40h 40h
Anybody know if it is possible to set up a formula on a set of 5 fields that
shows each person's utilization like this?
Thanks,
Al