K
Kris_Wright_77
I'm currently working on a project where the Fee is built up against tasks
using Generic Roles, which provides a Target Cost to the Client.
However, we also need to use Named Individuals for our own purposes to
ensure we can resource the job, and who may not necessarily be the same Fee
Rate as the Generic Role that they are fulfilling.
Worst Case I expect to have to have 2 identical programmes one resourced
with Generic roles and the other with Named Individuals.
But is there another way where I will only have to maintain a single
programme?
At the moment I think I assign both Generic and Named Resources to a Task,
and then use Custom Fields with formulae to separate out Hrs and Costs into
Target (Generic) & Actual (Named).
But having not used formulae within Project before, I am not sure whether
this is possible?
I'm sure I am not the first person to have this type of problem, so could
someone point me in the right direction?
BTW - Using Project Standard 2003
Thanks in advance for any help that anyone can give.
Kris W
using Generic Roles, which provides a Target Cost to the Client.
However, we also need to use Named Individuals for our own purposes to
ensure we can resource the job, and who may not necessarily be the same Fee
Rate as the Generic Role that they are fulfilling.
Worst Case I expect to have to have 2 identical programmes one resourced
with Generic roles and the other with Named Individuals.
But is there another way where I will only have to maintain a single
programme?
At the moment I think I assign both Generic and Named Resources to a Task,
and then use Custom Fields with formulae to separate out Hrs and Costs into
Target (Generic) & Actual (Named).
But having not used formulae within Project before, I am not sure whether
this is possible?
I'm sure I am not the first person to have this type of problem, so could
someone point me in the right direction?
BTW - Using Project Standard 2003
Thanks in advance for any help that anyone can give.
Kris W