S
spatton
We have a project that we would like all date change requests to be
approved by our department manager - however, the manager is not an
Admin and only accesses the project through Project Web Access (PWA).
Is it possible to forward these task changes to a resource who is not
an Admin?
Secondly, if our manager was an admin in the system could these be
sent to him?
The situation is that I (as project manager) want to continue
approving all tasks but date change requests - all date change request
we want approved by a manager.
Any suggestions or alternatives to the process would be welcome!
Thanks
Steve
approved by our department manager - however, the manager is not an
Admin and only accesses the project through Project Web Access (PWA).
Is it possible to forward these task changes to a resource who is not
an Admin?
Secondly, if our manager was an admin in the system could these be
sent to him?
The situation is that I (as project manager) want to continue
approving all tasks but date change requests - all date change request
we want approved by a manager.
Any suggestions or alternatives to the process would be welcome!
Thanks
Steve