Barry --
You can specify a resource as committed or proposed at the project level,
but not at the task level. To do so, open the project and then click
Tools - Build Team from Enterprise. In the Build Team dialog, set the
Booking value for each project team member to either Proposed or Committed
and then click OK. Click Collaborate - Publish - All Information. Team
members whose Booking type is Proposed will not see their tasks for the
project on their timesheet in PWA until you change the Booking type back to
Committed. Hope this helps.
You can specify a resource as committed or proposed at the project level,
but not at the task level. To do so, open the project and then click
Tools - Build Team from Enterprise. In the Build Team dialog, set the
Booking value for each project team member to either Proposed or Committed
and then click OK. Click Collaborate - Publish - All Information. Team
members whose Booking type is Proposed will not see their tasks for the
project on their timesheet in PWA until you change the Booking type back to
Committed. Hope this helps.