Possible to update Actual Work via the PSI?

T

tfz

Has anyone successfully updated Actual Work through the PSI? Based on other
posts in this group, I'm getting the impression that several people have
tried to do this, but noone has been successful. Is that a fair statement?

I understand that it is theoretically possible to do this, using
impersonation and some StatusUpdate calls, and the SDK is supposed to have an
example of using impersonation, and there are some blog entries showing how
to create the XML for the StautsUpdate calls, but I can't see where anyone
has successfully put it all together to update Actual Work via the PSI. I'm
just asking to see if I'm wasting my time by trying to do it through the PSI,
and should just go straight to a VBA method (which I don't really want to do,
but I will if I have to).

--tfz
 
U

UMAN

Hi,

I was able to update actual work through the psi. Have you seen anyhting
about updating actual cost through the PSI? That is where i am stuck.
 