Mike:
If you open the project using the Project client and publish, the indicator
should reappear. I don't think this problem is solved in SP1.
--
Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting:
http://www.msprojectexperts.com
For Project Server FAQS:
http://www.projectserverexperts.com
Thanks for your reply. I tested this setting change and it works!
We'll continue to test out all other features before we rollout SP1 to our
production servers.
Once again, thank you very much!
db said:
Nicky--
We had a similar issue and launched a ticket to MSFT about this--first
they
told us it was not possible, then we pushed for a better answer and it
turns
out there is a settings change needed (this is from our post --see posts
from
12/21 relating to My Tasks):
The answer eventually came as a setting. If you want the enterprise
fields
you input at the tasks level to be "pushed" to the assignment level
then go
toSERVER SETTINGS-->ENTERPRISE CUSTOM FIELD DEFINITION-->(SELECT
FIELD) then --> EDIT CUSTOM FIELD, find the "Calculation for
Assignment Rows", and select
"Roll Down". Additionally, you must publish all schedules to have this
data appear (even if they have previously been published,
unfortunately).
Try this setting change and see what results from a test with one
project.
It fixed our very similar issue.
Best of luck.
:
Hi Gary,
Glad to hear that your systems do not have this behaviour.
Here it goes:
1. Go to PWA > Server Settings > Enterprise Custom Field Definition >
New
Field. Enter as follows:
Name: Project Code
Entity=Task
Type=Text
Custom attributes=None
Calculation for Summary/Assignment rows=None
Values to display=Data
Required=Yes
2. Open MS Project Professional 2007, open an existing project file as
Read/Write.
3. Under Gantt Chart view > Insert a new column "Project Code
(Enterprise)"
4. Since this field cannot be blank, enter some values for all the
rows.
5. Save and Publish the project file.
6. Go back to PWA > Server Settings > Manage Views.
7. Under My Work > My Assignments > click on this to open the view
definition.
8. Add "Project Code [Task]" column to "Displayed fields". Press Save.
9. Now, go to My Tasks to see your own tasks. Notice the "Project
Code"
field is blank for all tasks.- Hide quoted text -
When tasks are first published the custom field is visible on My Task
page, however the problem I am seeing is that after the first round of
updates the custom value disappears from My Task page. Does anyone
else have ths same experience?
Mike- Hide quoted text -
- Show quoted text -