Hi All,
(Project Server Sp2/Aug CU)
I came across a potential bug in Project Server 2007.
Here is the scenario...
1. Create an enterprise lookup table and call it Application Name. Populate
this with values.
2. Create an enterprise custom field (task/text) called Application Name and
link it to the lookup table create in step1.Also select the values to roll
down to assignments
3. Create a plan with some tasks and assign those tasks to resources. Add
the custom fields to the gant chart and populate the task lines with values.
4. Save and Publish the plan
5. Have the resource create a timesheet and you can see the values are
populated. so this works as expected.
6. Now create a surrogate timesheet for the resource and the custom values
do not get populated.
Is this a bug or am I missing a setting or step?
Tks,
Shane
(Project Server Sp2/Aug CU)
I came across a potential bug in Project Server 2007.
Here is the scenario...
1. Create an enterprise lookup table and call it Application Name. Populate
this with values.
2. Create an enterprise custom field (task/text) called Application Name and
link it to the lookup table create in step1.Also select the values to roll
down to assignments
3. Create a plan with some tasks and assign those tasks to resources. Add
the custom fields to the gant chart and populate the task lines with values.
4. Save and Publish the plan
5. Have the resource create a timesheet and you can see the values are
populated. so this works as expected.
6. Now create a surrogate timesheet for the resource and the custom values
do not get populated.
Is this a bug or am I missing a setting or step?
Tks,
Shane