I just turn on the Tracking Period mechanism to enable/desable period of
allowed time entry.
On some project, when the Project Manager open them in MSP/pro, they
received the following message:
"Your project Server's tracking setting was changed since you last save this
project.
To prevent the potential loss of actuals in your project, you should avoid
saving this project to project Server. Contact your server administrator to
update projectServer with the actuals recorded in your project."
Does anyone know what this message mean exactly ?
Why the PM should AVOID SAVING the project ?
Why the potential loss of actuals ?
I just turn on the Tracking Period mechanism to enable/desable period of
allowed time entry.
On some project, when the Project Manager open them in MSP/pro, they
received the following message:
"Your project Server's tracking setting was changed since you last save this
project.
To prevent the potential loss of actuals in your project, you should avoid
saving this project to project Server. Contact your server administrator to
update projectServer with the actuals recorded in your project."
Does anyone know what this message mean exactly ?
Why the PM should AVOID SAVING the project ?
Why the potential loss of actuals ?