D
Dominik
I’m right now during an implementation of EPM 2007. We have an requirement to
use ManDays as main (and only) resource allocation unit in PPS. As everyone
knows PPS uses FTE’s. I’ve noticed that if you change resource rates
appropriately, you will be able to use ManDays in whole PPS instead of FTS’s.
And everything works correctly (only in PPS)!
The problem is with PPS and PS synchronization. Project Gateway do not
support ManDays. So if I update resource information in PPS from PS (budget
resource, resource actuals or forecasts), I get resource information in
FTS’s. So, I’m loosing data consistency…
Is there any way (programmatically or using configuration) to force resource
synchronization using ManDay’s in PPS?
One solution that we are considering is to write our own synchronization
engine. The problem is that it is huge interference in PPS dabatabase. And
our experiences with PPS db says that is very risky… (there are many, many
undocumented correlations in that DB and PPS logic…)
use ManDays as main (and only) resource allocation unit in PPS. As everyone
knows PPS uses FTE’s. I’ve noticed that if you change resource rates
appropriately, you will be able to use ManDays in whole PPS instead of FTS’s.
And everything works correctly (only in PPS)!
The problem is with PPS and PS synchronization. Project Gateway do not
support ManDays. So if I update resource information in PPS from PS (budget
resource, resource actuals or forecasts), I get resource information in
FTS’s. So, I’m loosing data consistency…
Is there any way (programmatically or using configuration) to force resource
synchronization using ManDay’s in PPS?
One solution that we are considering is to write our own synchronization
engine. The problem is that it is huge interference in PPS dabatabase. And
our experiences with PPS db says that is very risky… (there are many, many
undocumented correlations in that DB and PPS logic…)