E
Ed
Hello everyone, I am recently starting to get involved with Project, and
there is something I can't figure out how to do and I am not sure if it is
possible. There are some tasks which have a Predecessor task which is not
linked to any other.
For example the case where I would have to build a "Concrete Floor-Slab",
and after I have it ready I can put "Marble Floor" in it, the building
sequence is Concrete floor-slab and then Marble Floor with a FS relationship,
but I would like to have a "Pre-task" for Marble Floor, which is "Ordering"
it, and that task has a Duration of 4 weeks, so to be able to start with
Marble Floor, I would need to be done with Concrete Floor-slab, and Ordering,
but Ordering task has no predecessor, I just need to do it 4 weeks before
starting Marble Floors.
What I have done so far is just to put "Ordering" with a FS relationship to
Marble Floors, and just manually move it have the Finish date when "Marble
Foor" starts, the problem is when other activities change Marble Floor moves
forward or backward in time, and Ordering stays still. That is because
Ordering is taken as a activity that needs to start n day, is there a way to
do it the other way around? I mean to "anchor" the Finish date of Ordering to
the Start of Marblefloors and have the Start of Ordering varying?
The whole idea is to be able to incorporate to my program, the "Ordering" or
"Pre-fab" times for some special activities, for the construction to be able
to run smoothly.
I hope I was able to explain myself!
thanks in advance,
Ed
there is something I can't figure out how to do and I am not sure if it is
possible. There are some tasks which have a Predecessor task which is not
linked to any other.
For example the case where I would have to build a "Concrete Floor-Slab",
and after I have it ready I can put "Marble Floor" in it, the building
sequence is Concrete floor-slab and then Marble Floor with a FS relationship,
but I would like to have a "Pre-task" for Marble Floor, which is "Ordering"
it, and that task has a Duration of 4 weeks, so to be able to start with
Marble Floor, I would need to be done with Concrete Floor-slab, and Ordering,
but Ordering task has no predecessor, I just need to do it 4 weeks before
starting Marble Floors.
What I have done so far is just to put "Ordering" with a FS relationship to
Marble Floors, and just manually move it have the Finish date when "Marble
Foor" starts, the problem is when other activities change Marble Floor moves
forward or backward in time, and Ordering stays still. That is because
Ordering is taken as a activity that needs to start n day, is there a way to
do it the other way around? I mean to "anchor" the Finish date of Ordering to
the Start of Marblefloors and have the Start of Ordering varying?
The whole idea is to be able to incorporate to my program, the "Ordering" or
"Pre-fab" times for some special activities, for the construction to be able
to run smoothly.
I hope I was able to explain myself!
thanks in advance,
Ed