Pred/Succ Task Form

B

Bill madison

Can you modify this task form to show the predecessor and
successors dates and floats?

Also, can the form be modified to show the driving
predecessor and successor as it P3 or Suretrak?
 
J

JackD

While looking at the gantt view, go to "window" menu, select split. By
default the task form will show up on the bottom. Right click anywhere
within the task form and select "predecessors and successors".

That is all you can do. The driving predecessor option is not available. It
is the biggest feature that I miss from P3.

-Jack
 