K
Kesari Suresh
Hi ,
How does a successor task date change at back end? What is the procedure for
that.
What does microsoft project do to make sure the successor tasks match the
predecressor task.
Can i replicate the same feature with a custom date field.
Example:i have a custom date1 field for a task which is a predecessor task
of another task. When i change the custom date1 field of predecessor task,
the successor task's custom date1 also should be changed.
Can any one help me in this regard.
Thanks a lot.
Kesari Suresh.
How does a successor task date change at back end? What is the procedure for
that.
What does microsoft project do to make sure the successor tasks match the
predecressor task.
Can i replicate the same feature with a custom date field.
Example:i have a custom date1 field for a task which is a predecessor task
of another task. When i change the custom date1 field of predecessor task,
the successor task's custom date1 also should be changed.
Can any one help me in this regard.
Thanks a lot.
Kesari Suresh.