Predecessor Types - Auto Start to Start Links

K

KenCat

I have several tasks that I linked, on closer inspection in the gantt view I
noticed they all linked with a start to start link type (Not Finish to Start
as I expected). Any ideas how they might of automatically selected this type
of predecessor. (No constraints set.)
Thanks in advance
Ken
 
C

Crook

Hello Ken!

AFAIK, there is no way to change the default link type. All new links are
FS. Look for some agent/actor that may have changed the link type after the
links were added.

HTH,
Crook
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top