predecessors and successors

I

Ingrid

I am using 4 project files linked to each other in a master
file. The predecessors and successors don't seem to have
any pattern for when they appear and when they don't. Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.

Any ideas how to get some consistency with these?

Thanks,
Ingrid
 
J

Jack D.

Ingrid said:
I am using 4 project files linked to each other in a master
file. The predecessors and successors don't seem to have
any pattern for when they appear and when they don't. Eg.
a task in one project(project A) may have three successors
in another one (project B), yet only two show up in project
A in the task list of a gantt chart.


I've tried turning the "show external sucessors" on and off
in Tools>Options but this doesn't actually hide them all or
show them all - I still get some showing and some not
showing.

Any ideas how to get some consistency with these?

Thanks,
Ingrid

I think that if all the subprojects are expanded then you will see the
linkages.
But other than that, I find that they are somewhat capricious.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP


+++++++++++++++++++
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top