Hi,

In each time I do copy & paste between 2 project in 2007, the Predecessors
don't copy.

Does anyone know the reason or the solution for that?

Thanks,
Ran.
 
J

Jan De Messemaeker

Hi,

I suppose you mean in Project Professional (although you posted this in the
server newsgroup)?
Predecessors do copy, but only those within the copied selection of tasks.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
R

Ran @Comverse

I meant to 2007 pro.
I just select the rows and copy paste them.
All the data is copied except to the predecessors.

Ran.
 
D

Dpelan

Hi,

Was there a resolution to this issue? I have a deployment schedule for
multiple sites. I would like to copy the schedule for the first site for the
followon sites. When I select the appropriate rows and then paste, the
predecessors data is blank. I would like it to adjust to the new copied
block. I seem to recall Project 2003 doing this with no issue. Thanks for
your help.

Darrell
 