K
kamranashraf.ansari
Dear All,
I am new to using MS Project, I have been having a problem as under,
I have several sub-projects which I am adding to my Master project.
they all are depended on each other, when I make predecessors it goes ok. but if I go to task information menu to add delay or FS,SS etc there is no predecessors listed there.
How to fix this problem so predecessors are listed there in the task info.
Regards
Kamran
I am new to using MS Project, I have been having a problem as under,
I have several sub-projects which I am adding to my Master project.
they all are depended on each other, when I make predecessors it goes ok. but if I go to task information menu to add delay or FS,SS etc there is no predecessors listed there.
How to fix this problem so predecessors are listed there in the task info.
Regards
Kamran