Josh Whitney
I entered about 30 tasks in a row, some subtasks and some tasks. All
started and ended on the same day.
Now that I have them entered, I wanted to go back and link in predecessor
tasks but the start date doesn't adjust.
Task 1 starts 1/5/04 Ends 1/10/04
Task 10 Starts 1/5/04 Ends 1/6/04
I wanted Task 10 to be dependent on Task 1 ending, so I linked 1 to 10, but
the start date for 10 did not change.
Thanks for Any help?
started and ended on the same day.
Now that I have them entered, I wanted to go back and link in predecessor
tasks but the start date doesn't adjust.
Task 1 starts 1/5/04 Ends 1/10/04
Task 10 Starts 1/5/04 Ends 1/6/04
I wanted Task 10 to be dependent on Task 1 ending, so I linked 1 to 10, but
the start date for 10 did not change.
Thanks for Any help?