Predecessors won't update

R

ramon38

I updated my project with a new task and all the task that followed would not
update their dates based off of the new task, nor would the respond to
changes to any of the other tasks either. Can anyone help me out?

Thanks,
 
J

JulieS

Hello ramon38,

Press F9 to manually recalculate the project. Then set your
calculation to automatic through Tools > Options, Calculation tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 