N
Norman Sanin
I have a problem where I told MS Project Pro 2003 to remove leveling, but
some tasks still have preleveled starts or finishes that are different from
their start/finish dates. I believe this occured when I leveled, made some
work contour and resource assignment changes to my schedule, and leveled
again. I did not like the subsequent results, so I asked it to remove all
leveling. All leveling delays seem to be removed, but start & finsih dates
were not returned to their original values. I am aware that the Remark on
the Preleveled Start (task field) entry within MS Project help states
"Remarks You can use the Leveling Gantt view to see the preleveled start
date shown with the preleveled Gantt bars. Once you've leveled the project,
specific tasks will have preleveled start dates that you cannot remove."
Has anyone found a work around? Any help would greatly be appreciated.
Norman Sanin
some tasks still have preleveled starts or finishes that are different from
their start/finish dates. I believe this occured when I leveled, made some
work contour and resource assignment changes to my schedule, and leveled
again. I did not like the subsequent results, so I asked it to remove all
leveling. All leveling delays seem to be removed, but start & finsih dates
were not returned to their original values. I am aware that the Remark on
the Preleveled Start (task field) entry within MS Project help states
"Remarks You can use the Leveling Gantt view to see the preleveled start
date shown with the preleveled Gantt bars. Once you've leveled the project,
specific tasks will have preleveled start dates that you cannot remove."
Has anyone found a work around? Any help would greatly be appreciated.
Norman Sanin