T
Tricky
I have inherited a schedule that has been set up for effort driven fixed
work, 12 hours per day (7 day week), with some resources allocated to a 7 day
standard calendar, and some to a 24 hour calendar.
The reason for my question is that this schedule of works is a 24 hours
operation, so is it right that the calendar (in options) is set up for 12
hours, and individual resources set up for 24 hours...
....or should the project calendar be set for 24 hours, with individual
resources set for whichever pattern they are working.
I suspect that it should be the latter.
If that is the case, is it just straight forward to change to the 24 hour
calendar?
The added complication i'm facing is that i historically have used fixed
duration (not effort driven) as i need to add in codings to the resource info
of an activity, that allow me to see information graphically, but do not have
a bearing on the number of people carrying out that job ie total persons on
site, bedding requirements etc.
Can i therefore preserve the duration of these jobs when chaging over from
fixed units to fixed duration having changed the calendar (to 24h), and in
which order do i need to do things in????
Hope this all makes sense
thanks in advance
work, 12 hours per day (7 day week), with some resources allocated to a 7 day
standard calendar, and some to a 24 hour calendar.
The reason for my question is that this schedule of works is a 24 hours
operation, so is it right that the calendar (in options) is set up for 12
hours, and individual resources set up for 24 hours...
....or should the project calendar be set for 24 hours, with individual
resources set for whichever pattern they are working.
I suspect that it should be the latter.
If that is the case, is it just straight forward to change to the 24 hour
calendar?
The added complication i'm facing is that i historically have used fixed
duration (not effort driven) as i need to add in codings to the resource info
of an activity, that allow me to see information graphically, but do not have
a bearing on the number of people carrying out that job ie total persons on
site, bedding requirements etc.
Can i therefore preserve the duration of these jobs when chaging over from
fixed units to fixed duration having changed the calendar (to 24h), and in
which order do i need to do things in????
Hope this all makes sense
thanks in advance