Prevent Task Publishing in Server 2003

K

KevinM

We are running Project Server 2003 using Managed Time Periods. We're trying
to simplify our time tracking requirements by only publishing certain tasks
to PWA while keeping most of the tasks unpublished.

We'd like to use Enterprise Resources for all of the tasks so our resource
forecast information is accuarate. In other words, we don't want to use
local resources for the "planning" tasks and enterprise resources for the
"time tracking" tasks.

Is there any practical way to prevent certain tasks from being automatically
republished when our PM's accept time into the plan?

Thanks.

Kevin
 
G

Gary Chefetz

I'm not sure that this is what you want to hear, but your most practical
solution all around would be to upgrade to 2007, which handles this rather
elegantly.
 
K

KevinM

Gary,

Thanks very much for your reply.

Gary Chefetz said:
I'm not sure that this is what you want to hear, but your most practical
solution all around would be to upgrade to 2007, which handles this rather
elegantly.
 