I would like to know if there is a way to retain the settings on the three
tier timescale when changing the zoom.
The project runs from October to the end of March. I set the tiers as year,
month, week. I then click view, zoom, entire project. This makes the top
two tiers change units into months (with a count of two) and thirds of a
month (with a count of three).
Any help much appreciated.
John
Hi,
I would like to know if there is a way to retain the settings on the three
tier timescale when changing the zoom.
The project runs from October to the end of March. I set the tiers as year,
month, week. I then click view, zoom, entire project. This makes the top
two tiers change units into months (with a count of two) and thirds of a
month (with a count of three).
Any help much appreciated.