Preventing rounded values

P

Pedro Teves

Hi,

I am importing the work and actualwork values from a plan into a
master one, and somethimes the values imported to the master plan
loose 0,01 days during the process. I'm assuming that project is some
how rounding the values.

Can any one tell me something that I can do to prevent project from
rounding thoose values.

Thanks in advanced
 
J

JackD

0.01 days = about 5 minutes. About enough time to go to the bathroom or
answer a phone call. Are you sure your estimates of work are so precise? I'd
just ignore it.
 
P

Pedro Teves

Hi,

The problem is not loosing 5 min of work. The problem is to have 1day
of work and 0,99 days of actual work. This causing a task that should
already been completed to be at 99% and pushing the finish date to the
status date.

Pedro.
 