Preventing task going accross two days

S

serene

I have MS Poject sort all of my jobs by priority then
schedule them based on based on available resources. All
jobs are less then a day in duration so when the next job
will not fit into the balance of a day, I want it to be
moved to the next day. To complicate matters I then want
project to identify the next highext priority job that
can be scheduled into what was left of the previous day.

Any suggestions or am I asking to much?
 
R

Rod Gill

Hi,

Project levelling can't do this, it tries to finish all tasks in the
shortest time. You could however write a VBA macro to do this, but I don't
know whether this would be worthwhile?

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
S

serene

Ron,

Thanks for the feedback.

Regards,

serene
-----Original Message-----
Hi,

Project levelling can't do this, it tries to finish all tasks in the
shortest time. You could however write a VBA macro to do this, but I don't
know whether this would be worthwhile?

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/



.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top