Printing a report of % completed?

  • Thread starter Printing a report of % completed?
  • Start date
P

Printing a report of % completed?

Hi, is there a way in project 2002 to print a report that merely tells you all the work that has 'not' yet been completed and what their %'s are?

Right now I have a custom column that is % complete, my boss has given me the oh so fun task of figuring out how to just print the report based on that column, whats left to work on and the percent. Please help =)

-Jason
 
J

JackD

I'm not much for the built-in reports in project, but the first thing you
need to do is to create a filter which will show only tasks that have not
yet been completed.

There is a built-in "in progress" filter which you could use. If the custom
column is the one that you are going to filter on, then you will need to
create your own filter. Once you have a filter which works just create a
custom task report which uses that filter.
It should be pretty close.

-Jack

"Printing a report of % completed?" <Printing a report of %
[email protected]> wrote in message
Hi, is there a way in project 2002 to print a report that merely tells you
all the work that has 'not' yet been completed and what their %'s are?
Right now I have a custom column that is % complete, my boss has given me
the oh so fun task of figuring out how to just print the report based on
that column, whats left to work on and the percent. Please help =)
 
R

Rajkumar

Hi

You could try the following option

Use the filter "Incomplete tasks" (Project --> Filtered
for -->Incomplete task). This extracts the tasks that are
not complete (ie., % complete<100%)
To create the report of above tasks , you could use View -
->Reports --> choose "Current activities" -->
click "Select" --> choose "Completed activities" -->click"
EDIT" --> Change the filter option to " Incomplete task"--
click OK --> click "Select" and this displays the
report of uncompleted task

M Rajkumar

-----Original Message-----

-----Original Message-----
Hi, is there a way in project 2002 to print a report that
merely tells you all the work that has 'not' yet been
completed and what their %'s are?
Right now I have a custom column that is % complete, my
boss has given me the oh so fun task of figuring out how
to just print the report based on that column, whats left
to work on and the percent. Please help =)
 