C
Costelu
Hi,
I would like to know if it is possible to adapt my project calendar so that
it takes into account only those days on which construction outside is
possible.
I've been told that in some other project tools it is possible for the
project calendar to take in consideration the elements of rain, extreme cold
and other factors that keep the construction crew from working.
But, we want to see a double timescale and only one task in the gantt chart
view. The upper timescale shows the end date of the task based on the
project calendar and the second timescale shows the equivalent date which
takes into account the extreme cold weather factors for example.
The purpose of this is, when you print the gantt chart view you get a quick
graphical overview on paper of the finish dates on both timescales of TASK1
(One Task bar, on top two Timescales).
Example :
TASK1 ENDDATE ON PROJECT TIMESCALE: 17/03/2005
TASK1 ENDDATE ON EQUIVALENT TIMESCALE: 21/03/2005
Thanks,
Lco
I would like to know if it is possible to adapt my project calendar so that
it takes into account only those days on which construction outside is
possible.
I've been told that in some other project tools it is possible for the
project calendar to take in consideration the elements of rain, extreme cold
and other factors that keep the construction crew from working.
But, we want to see a double timescale and only one task in the gantt chart
view. The upper timescale shows the end date of the task based on the
project calendar and the second timescale shows the equivalent date which
takes into account the extreme cold weather factors for example.
The purpose of this is, when you print the gantt chart view you get a quick
graphical overview on paper of the finish dates on both timescales of TASK1
(One Task bar, on top two Timescales).
Example :
TASK1 ENDDATE ON PROJECT TIMESCALE: 17/03/2005
TASK1 ENDDATE ON EQUIVALENT TIMESCALE: 21/03/2005
Thanks,
Lco