J
Jason
Hello,
I have a project that is over 2 weeks long but there are
some days, where nothing will be done with the project.
So these days show completely blank like there is no
activity. Is there anyway to have MS Project skip these
days when I print it, so I am not printing blank sheets?
Thanks for the assistance.
I have a project that is over 2 weeks long but there are
some days, where nothing will be done with the project.
So these days show completely blank like there is no
activity. Is there anyway to have MS Project skip these
days when I print it, so I am not printing blank sheets?
Thanks for the assistance.